Slide
notes: The Human Skills planning reports are 'date range' based and will
only report on Events that have been assigned a Start Date.
Slide 2
Slide
notes: We can perform the Skills Planning report by Works Order to see the
Skills assigned to each Works Order.
Slide 3
Slide
notes:
Slide 4
Slide
notes: And we can select the Date Range for the Report result, i.e. by
Event Start Date.
Slide 5
Slide
notes:
Slide 6
Slide
notes: This is an example of the Report, and it shows Skills assignment by
Works Order.
Slide 7
Slide
notes: We can also perform the Skills Planning Report by Person.
Slide 8
Slide
notes: And again, we can select the date range for Events to be included.
Slide 9
Slide
notes:
Slide 10
Slide
notes: The 'Skills Assignment by Person' Report will show for each Person
assigned, the total hours per Works Order, and also the total Hours per
Date, so if a Person is over-assigned for any Date, then it will be clearly
shown here.